While the Columbia-Adair County Economic Development Authority was recently awarded funding for KPDI Round 2, they are still working on the completion of Park improvements associated with KPDI Round 1. These improvements include water, sewer, and gas line extensions, as well as a new lift station for sewer on the North side of the Park.
According to EDA consultant Heather Spoon, a hard copy of the Bid Package was received on Friday afternoon, March 1st, 2024 and can be viewed at Adair County Judge Exec. Larry Russell Bryant's office Monday-Friday, 8:00am-4:00pmCT. The package can also be viewed on MSE of Lexington's website, www.mselex.com, and selecting "GRCP Water, Sewer and Gas Line Extensions to Lot 3" from the Bid Opportunities tab.
These improvements are very important to the readiness of Green River Commerce Park and will stimulate our economy as hundreds of thousands of dollars will be invested and awarded!