Russell County Fiscal Court Holds First Reading on Solar Ordinance Wednesday
The first reading came before the Fiscal Court yesterday morning. Items included in the ordinance…
A setback no less than 2,000 feet from any non-participating property line or publicly-maintained roadway.
Access to the site would be controlled by a fence at least 8-feet high with a vegetative landscape buffer provided between the fencing and property line.
The judge-executive can revoke the company’s license if the company fails to abide by the ordinance. The judge-executive would send a notice to the company, and the company would have 90 days to correct the violations. If they do not, the license could be revoked.
Wednesday was the first reading. The ordinance would be voted on after the 2nd reading, also changes can be made to the ordinance before the vote.