The date for the road closure at Wolf Creek Dam has changed. It will not be closed on June 2, 2026. Instead, it will be closed on May 27, 2026.
As part of the rehabilitation of the spillway gates at Wolf Creek Dam, both lanes of US 127 across the Dam will be closed on Wednesday, May 27, 2026 from 8:00 AM to 4:00 PM. Message boards will be placed at predetermined sites to provide additional information.
Accommodations will be made for emergency and school traffic as required.
American Bridge will turn off the message boards when the road can be opened should it not require the full duration.
7 days prior to closure, message boards will show:
Screen 1 Screen 2
US 127 @ Closed
Wolf Creek May 27
Dam 8AM- 4PM
Day of closure, the boards will show:
Screen 1 Screen 2
US 127 XX Miles (distance dependent on where board is placed)
Closed Ahead